NTPC has formulated a long term Corporate Plan to become a 130 GW company upto 2032. In line with the Corporate Plan, the capacity addition under implementation presently:
No. | PROJECT | STATE | MW |
---|---|---|---|
NTPC | |||
1. | Barh-I | Bihar | 660 |
2. | Tapovan Vishnugud-Hydro | Uttarakhand | 520 |
3. | Lata Tapovan-Hydro | Uttarakhand | 171 |
4. | North Karanpura | Jharkhand | 1320 |
5. | Rammam-Hydro | West Bengal | 120 |
6. | Telangana | Telangana | 800 |
7. | TTPS-III | Odisha | 1320 |
8. | Lara-II | Chhattisgarh | 1600 |
Total | 6,511 | ||
JV & Sub. Companies | |||
1. | Durgapur-NSPCL | West Bengal | 20 |
2. | BIFPCL | Khulna | 660 |
3. | Patratu | Jharkhand | 2400 |
4. | Khurja-THDC | Uttar Pradesh | 1320 |
5. | Tehri PSP-THDC | Uttarakhand | 1000 |
6. | Pipalkoti-THDC | Uttarakhand | 444 |
Total | 5,844 | ||
Grand Total (NTPC + JV & Sub. Companies) | 12,355 |