Power Generation

Renewable Energy

NTPC is taking various steps to make its energy portfolio greener by adding significant capacities of Renewable Energy(RE) Sources. By 2032, the company plans to have a minimum of 32000 MW capacity through RE sources constituting nearly 25% of its overall power generation capacity.

Own Capacity Addition

A) Commissioned Projects : NTPC has a commissioned capacity of 928 MW of RE projects under own capacity addition. The details of projects are as under:

Commissioned Projects

Sr. No.ProjectState/UTCapacity (MW)
ASolar  
1.Dadri Solar PVUttar Pradesh5
2.Port blair Solar PVAndaman & Nicobar Island5
3.Ramagundam Solar PV (Phase -I)Telangana10
4.Talcher Kaniha Solar PVOdisha10
5.Faridabad Solar PVHaryana5
6.Unchahar Solar PVUttar Pradesh10
7.Rajgarh Solar PVMadhya Pradesh50
8.Singrauli Solar PVUttar Pradesh15
9.Ananthapuram Solar PVAndhra Pradesh250
10.Bhadla-SolarRajasthan260
11.Mandsaur-Solar PVMadhya Pradesh250
BWind  
 RojmalGujarat50
CSmall Hydro  
 Singrauli SHPUttar Pradesh8
 Total928

B) Projects Under Implementation :

2298 MW of RE projects are under implementation. Out of which 237 MW constitutes floating solar projects located in reservoirs in NTPC’s existing stations. Ramagundam 100 MW Floating Solar being set up under non PPA mode is the largest in the country. The details of projects are as under :

Projects under Implementation : 2298 MW

Sr. No.ProjectState/UTSolar-G/FMW
1.BilhaurUttar PradeshSolar-G140
2.BilhaurUttar PradeshSolar-G85
3.AuraiyaUttar PradeshSolar-G20
4.RamagundamAndhra PradeshSolar-F100
5.SimhadriAndhra PradeshSolar-F25
6.KayamkulamKeralaSolar-F22
7.KayamkulamKeralaSolar-F70
8.JetsarRajasthanSolar-G160
9.RihandUttar PradeshSolar-G20
10.AuraiyaUttar PradeshSolar-F20
11.CPSU-I: Shimbhoo Ka BurjRajasthanSolar-G250
12.CPSU-I: DevikotRajasthanSolar-G150
13.CPSU-I: Shimbhoo Ka BurjRajasthanSolar-G300
14.CPSU-II: NokhraRajasthanSolar-G300
15.CPSU-II: FatehgarhRajasthanSolar-G296
16.CPSU-II: NavalakhapattiTamilnaduSolar-G230
17.CPSU-II: DevikotRajasthanSolar-G90
18.CPSU-I: GandharRajasthanSolar-G20
 TOTAL2298
(G- Ground Mounted, F – Floating )

Developer Mode Projects

NTPC acts as an intermediary procurer where it procures power from the Developers and sells to DISCOMs with a trading margin

3983 MW of RE projects has been commissioned under Developer Mode so far.

2. JV/ Subsidiary RE Projects

A. Operational Projects

StationStateTypeCapacity (MW)
Dhukwan SHP (3 X12) (THDC)UttarPradeshSmall Hydro24
Patan Wind Power Project(THDC)GujaratWind50
Devbhumi Dwarka Wind Power Project(THDC)GujaratWind63
Solar TGBPP Tripura (NEEPCO)TripuraSolar5
Total  142

B. Projects Under Implementation

StationStateTypeCapacity (MW)
THDC- Kasargod Solar PVKeralaSolar50
Total  50

 

Renewable Power plant by NTPC