Power Generation

Renewable Energy

NTPC is taking various steps to make its energy portfolio greener by adding significant capacities of Renewable Energy(RE) Sources. By 2032, the company plans to have a minimum of 32000 MW capacity through RE sources constituting nearly 25% of its overall power generation capacity.

NTPC is pursuing capacity addition in Renewable Energy projects in two modes namely Own capacity addition mode and Developer Mode.

In Own capacity addition mode, NTPC sets up Renewable Energy projects on its own investment. In Developer Mode, NTPC acts as an intermediary procurer where it procures power from the Developers and sells to DISCOMs with a trading margin.

Own Capacity Addition

A) Commissioned Projects : NTPC has a commissioned capacity of 920 MW of RE projects under own capacity addition. The details of projects are as under:

Commissioned Projects

Sr. No.ProjectState/UTCapacity (MW)
ASolar  
1.Dadri Solar PVUttar Pradesh5
2.Port blair Solar PVAndaman & Nicobar Island5
3.Ramagundam Solar PV (Phase -I)Telangana10
4.Talcher Kaniha Solar PVOdisha10
5.Faridabad Solar PVHaryana5
6.Unchahar Solar PVUttar Pradesh10
7.Rajgarh Solar PVMadhya Pradesh50
8.Singrauli Solar PVUttar Pradesh15
9.Ananthapuram Solar PVAndhra Pradesh250
10.Bhadla-SolarRajasthan260
11.Mandsaur-Solar PVMadhya Pradesh250
BWind  
 RojmalGujarat50
 Total920

B) Projects Under Implementation :

2298 MW of RE projects are under implementation. Out of which 237 MW constitutes floating solar projects located in reservoirs in NTPC’s existing stations. Ramagundam 100 MW Floating Solar being set up under non PPA mode is the largest in the country. The details of projects are as under :

Projects under Implementation : 2298 MW

Sr. No.ProjectState/UTSolar-G/FMW
1.BilhaurUttar PradeshSolar-G140
2.BilhaurUttar PradeshSolar-G85
3.AuraiyaUttar PradeshSolar-G20
4.RamagundamAndhra PradeshSolar-F100
5.SimhadriAndhra PradeshSolar-F25
6.KayamkulamKeralaSolar-F22
7.KayamkulamKeralaSolar-F70
8.JetsarRajasthanSolar-G160
9.RihandUttar PradeshSolar-G20
10.AuraiyaUttar PradeshSolar-F20
11.CPSU-I: Shimbhoo Ka BurjRajasthanSolar-G250
12.CPSU-I: DevikotRajasthanSolar-G150
13.CPSU-I: Shimbhoo Ka BurjRajasthanSolar-G300
14.CPSU-II: NokhraRajasthanSolar-G300
15.CPSU-II: FatehgarhRajasthanSolar-G296
16.CPSU-II: NavalakhapattiTamilnaduSolar-G230
17.CPSU-II: DevikotRajasthanSolar-G90
18.CPSU-I: GandharRajasthanSolar-G20
 TOTAL2298
(G- Ground Mounted, F – Floating )

Under CPSU scheme of MNRE, it is envisaged to set up solar projects using domestically manufactured Solar cells and Solar modules with Viability Gap Funding (VGF) support from MNRE. Under this scheme, NTPC has so far won 1692 MW under competitive bidding of SECI. Out of 1692 MW, award has been placed for 1636 as shown in above table and balance capacities are under tendering. 

Developer Mode Projects

Commissioned Projects :  3983 MW of RE projects  has been commissioned under Developer Mode so far

 

Renewable Power plant by NTPC