NTPC has formulated a long term Corporate Plan to become a 130 GW company upto 2032. In line with the Corporate Plan, the capacity addition under implementation presently:
No. | PROJECT | STATE | MW |
---|---|---|---|
NTPC | |||
1. | Barh-I | Bihar | 1980 |
2. | Tapovan Vishnugud-Hydro | Uttarakhand | 520 |
3. | Lata Tapovan-Hydro | Uttarakhand | 171 |
4. | Lara | Chhattisgarh | 800 |
5. | Gadarwara | Madhya Pradesh | 800 |
6. | Darlipali | Odisha | 800 |
7. | North Karanpura | Jharkhand | 1980 |
8. | Rammam-Hydro | West Bengal | 120 |
9. | Tanda-II | Uttar Pradesh | 660 |
10. | Telangana | Telangana | 1600 |
Total | 9,431 | ||
JV & Sub. Companies | |||
1. | Meja | Uttar Pradesh | 660 |
2. | Nabinagar-BRBCL | Bihar | 250 |
3. | Nabinagar-NPGC | Bihar | 1320 |
4. | Rourkela-NSPCL | Odisha | 250 |
5. | Durgapur-NSPCL | West Bengal | 40 |
6. | BIFPCL | Khulna | 1320 |
7. | Patratu | Jharkhand | 4000 |
Total | 7,840 | ||
Grand Total (NTPC + JV & Sub. Companies) | 17,931 |