NTPC has formulated a long term Corporate Plan to become a 130 GW company upto 2032. In line with the Corporate Plan, the capacity addition under implementation presently:
No. | PROJECT | STATE | MW |
---|---|---|---|
NTPC | |||
1. | Barh-I | Bihar | 1980 |
2. | Tapovan Vishnugud-Hydro | Uttarakhand | 520 |
3. | Lata Tapovan-Hydro | Uttarakhand | 171 |
4. | North Karanpura | Jharkhand | 1980 |
5. | Rammam-Hydro | West Bengal | 120 |
6. | Telangana | Telangana | 1600 |
7. | Barauni | Bihar | 1980 |
Total | 8,351 | ||
JV & Sub. Companies | |||
1. | Nabinagar-BRBCL | Bihar | 250 |
2. | Durgapur-NSPCL | West Bengal | 40 |
3. | BIFPCL | Khulna | 1320 |
4. | Patratu | Jharkhand | 4000 |
5. | Khurja-THDC | Uttar Pradesh | 1320 |
6. | Tehri PSP-THDC | Uttarakhand | 1000 |
7. | Pipalkoti-THDC | Uttarakhand | 444 |
Total | 8,374 | ||
Grand Total (NTPC + JV & Sub. Companies) | 16,725 |