Power Generation

Simhadri

NTPC Simhadri

Address
P.O. Simhadri-531 020, Dist. Vishakhapatnam, Andhra Pradesh
Telephone
(STD-08924,STD-Vizag-0891) - 243001
Fax
243092
Approved capacity
2000 MW
Installed Capacity
2000 MW
Location
Near Pittavanipalem Village,Dist. Vishakhapatnam, Andhra Pradesh
Coal Source
Kalinga Block of Talcher Coal fields in Orrisa
Water Source
Yeluru canal for sweet water, Sea water for CW system.
Beneficiary States
Andhra Pradesh (100%) .
Approved Investment
Rs.3650.79 Cr.(I Qtr.97).
Units Commissioned
Unit-I Commissioning: Feb 2002
Unit-II Commissioning: Aug 2002
Unit-III Commissioning: Mar 2011
Unit-IV Commissioning: Mar 2012
International Assistance
JBIC
Govt. approved date
24.07.1997 (Zero date 08.07.1997)
Land Availability
3384.24 acres (entire land)
Associated Transmission System
Implemented by APTRANSCO.
Associated Transmission System
Implemented by APTRANSCO.
Plant Configuration
4X500 MW