Power Generation

Ramagundam

NTPC Ramagundam

Address
P.O. Jyothinagar,Dist. Karim Nagar-505 215, Telangana
Telephone
(STD-08728) - 272125
Fax
272122
Approved capacity
2600 MW
Installed Capacity
Stage I : 3X200 MW Stage II : 3X500 MW Stage III : 1X500 MW
Location
Karimnagar, Telangana
Coal Source
(i) South Godavari Coal Fields of Singrani Collieries for Stage I & II (ii) Korba Coal Fields of SECL for Stage III
Water Source
Sri Ram Sagar Dam on Godavari River, D-83 Canal from pochampad Reservoir
Beneficiary States
Pondicherry, Goa, Kerala, Karnataka, Tamil Nadu, Telangana, PGCIL (for HVDC)
Approved Investment
Rs. 2059.22 Cr Stage I & II Rs. 1818.46 Cr Stage III
Unit Sizes
Stage - I: 3x 200 MW
Stage -II: 3x 500 MW
Units Commissioned
Unit -I 200 MW November 1983
Unit -II 200 MW May 1984
Unit -III 200 MW December 1984
Unit -IV 500 MW June 1988
Unit -V 500 MW March 1989
Unit -VI 500 MW October 1989
Unit Commissioned Shedule
Unit -VII 500 MW August 2004
International Assistance
IDA IBRD loan OPEC KFW EXIM Bank, Japan. SFD